Hyperion data center (Louisiana)

Meta raised the planned capacity of the Richland Parish, Louisiana campus from 2 GW to 5 GW, with total investment above $50B.

META market data

The numbers

Planned compute capacity5 GWJuly 2026 · up from more than 2 GW · source ↗
Total investmentmore than $50BJuly 2026 · up from $10B at the 2024 announcement · source ↗

What it is

Meta's largest AI data center, under construction in Richland Parish, Louisiana since December 2024. The site is financed through a joint venture, and power comes from new gas-fired plants that Entergy Louisiana plans to build for the site. Meta has also committed more than $1B to local infrastructure.

Why it matters to the stock. Hyperion sets how much compute Meta can add beyond 2027, and so how long the capex cycle lasts. Power approval and the build timeline are the main risks to that schedule.