Micron breaks ground on $100 billion New York megafab campus
Micron held a groundbreaking on January 16, 2026 for a planned $100 billion campus of up to four DRAM fabs in Onondaga County, New York. The first two fabs are set to begin DRAM output around 2030, and the other two are not scheduled to finish until 2041. Micron cites up to 50,000 jobs over about 20 years, which matters for capex and future bit supply rather than near-term revenue.
- Planned investment of $100 billion across up to four fabs
- DRAM production expected by 2030 from the first two fabs
- Other two fabs not scheduled to finish until 2041
- Up to 50,000 jobs, including 9,000 fab workers
Source
The RegisterJan 16, 2026